Search found 31 matches

by vantech2022
Sun Feb 12, 2023 7:41 pm
Forum: Photovoltaic
Topic: Solar panels on pergola - what is everyone doing?
Replies: 42
Views: 4290

Re: Solar panels on pergola - what is everyone doing?

Anybody any experience with bifacial panels? I think they let through more light, between cells. How to fix them(they are glass edged, no metal surround), how to keep water from dripping between panels? Are there any kits or designs out there for this kind of thing? There’s lots of space for a sout...
by vantech2022
Sat Feb 11, 2023 7:52 pm
Forum: Photovoltaic
Topic: Solar panels on pergola - what is everyone doing?
Replies: 42
Views: 4290

Solar panels on pergola - what is everyone doing?

Hi,

Planning on adding some panels to a pergola in the garden and looking for ideas and inspiration.

Wood or aluminium frame would be ideal.

Thanks.
by vantech2022
Sat Dec 10, 2022 3:30 pm
Forum: Photovoltaic
Topic: MCS for self installed solar
Replies: 13
Views: 4724

MCS for self installed solar

Hi, I have a self installed solar array. All registered with the DNO etc, and above board with regards to wiring regulations. Does anyone know if there is a way to get the install MCS (or other) certified, and if there is any point as the FIT is no more? I have read there is a smart export guarantee...
by vantech2022
Fri Nov 25, 2022 7:13 pm
Forum: Energy storage, batteries, energy tariffs
Topic: Net metering - export without FIT
Replies: 2
Views: 479

Net metering - export without FIT

Hi,

I have a smart meter and solar installed as a DIY, so I don’t have a FIT.

If I export to the grid, I know I won’t get paid, but will I get charged? I’ve read some older meters can’t differentiate between import and export.

How does this work when using smart meters?

Thanks.
by vantech2022
Thu Nov 24, 2022 9:35 pm
Forum: Energy storage, batteries, energy tariffs
Topic: G100 devices
Replies: 23
Views: 2355

Re: G100 devices

If you have two inverters connected to the grid, say a PV inverter and a battery system inverter, then the export sum of both has to remain within whatever limit the DNO will allow under G99 (which used to be called G59). This also applies if you have two G98 (used to be G58) compliant inverters, s...
by vantech2022
Thu Nov 24, 2022 9:35 pm
Forum: Energy storage, batteries, energy tariffs
Topic: G100 devices
Replies: 23
Views: 2355

Re: G100 devices

Because the G100 device has a CT clamp sensor at the grid point so it knows whether the house is exporting or importing and by how much. OK, say you have one G98 3.68kW inverter with no export control and one ESS inverter which is essentially a zero export inverter and the batteries are full. Yes t...
by vantech2022
Thu Nov 24, 2022 8:55 pm
Forum: Energy storage, batteries, energy tariffs
Topic: G100 devices
Replies: 23
Views: 2355

Re: G100 devices

By throttling back, think of a dimmer switch on a light bulb. I understand that, what I don’t understand is the following scenario. If the ESS is supplying loads, and solar production begins, it won’t see a demand and in theory, if the solar inverter is set to zero export, it will sit there idling?...
by vantech2022
Thu Nov 24, 2022 8:24 pm
Forum: Energy storage, batteries, energy tariffs
Topic: G100 devices
Replies: 23
Views: 2355

G100 devices

Hi, When applying for G99, does both the solar inverter and the ESS need G100, or only one of the devices? I am assuming one of them, to limit the total export. The question I have is for solar arrays. If the battery is full, and the solar array is producing full power, how will the solar inverter p...
by vantech2022
Thu Nov 24, 2022 7:49 pm
Forum: Energy storage, batteries, energy tariffs
Topic: Enphase with Alpha ESS
Replies: 4
Views: 614

Re: Enphase with Alpha ESS

Thanks. The alpha battery has G100 export limitation, set to zero export. This means that it does not export to the grid, so even if the solar inverter is at full output (G98) the battery does not export. The question I suppose is does the Enphase inverter need to be set to zero export? I hadn't re...
by vantech2022
Wed Nov 23, 2022 6:56 pm
Forum: Energy storage, batteries, energy tariffs
Topic: G99 fast track commissioning
Replies: 7
Views: 835

Re: G99 fast track commissioning

Hi, Permission was granted and all documents for the inverters etc approved. They will be contacting me for commissioning forms. The system just works, and does exactly as it should. This was self installed (complaint with Part P etc). When they call, I just need to know what they’ll ask for. Print...