Lots more batteries to be connected to the grid in the next 12 months or so...

https://renews.biz/95159/edf-renewables ... ge-online/
Tesla Model 3 Performance
Oversees an 11kWp solar array at work
Lincs Robert
Posts: 214
Joined: Fri Mar 11, 2022 7:48 pm
Location: Lincolnshire

Re: EDF to bring 300MW of BESS online

#2

Post by Lincs Robert »

Was I the only one to notice the probable error in this headline? 300MW? Surely it’s 300MWh? Power stations are rated by power output, which is a continuous measure. Storage should be correctly described - IMO of course ……
Countrypaul
Posts: 572
Joined: Sun Jul 18, 2021 11:50 am

Re: EDF to bring 300MW of BESS online

#3

Post by Countrypaul »

Lincs Robert wrote: Fri Aug 23, 2024 6:33 pm Was I the only one to notice the probable error in this headline? 300MW? Surely it’s 300MWh? Power stations are rated by power output, which is a continuous measure. Storage should be correctly described - IMO of course ……
I think this has been raised before, iirc one opinion is that since it will be a source of power then the power should be quoted. I tend o agree with you that the energy content shold be quoted, but quoting both would make things clearest as has been done wth the Iron-Air thread.
Lincs Robert
Posts: 214
Joined: Fri Mar 11, 2022 7:48 pm
Location: Lincolnshire

Re: EDF to bring 300MW of BESS online

#4

Post by Lincs Robert »

Countrypaul wrote: Fri Aug 23, 2024 7:05 pm
Lincs Robert wrote: Fri Aug 23, 2024 6:33 pm Was I the only one to notice the probable error in this headline? 300MW? Surely it’s 300MWh? Power stations are rated by power output, which is a continuous measure. Storage should be correctly described - IMO of course ……
I think this has been raised before, iirc one opinion is that since it will be a source of power then the power should be quoted. I tend o agree with you that the energy content shold be quoted, but quoting both would make things clearest as has been done wth the Iron-Air thread.
+ 1. Sorted
User avatar
nowty
Posts: 5794
Joined: Mon May 31, 2021 2:36 pm
Location: South Coast

Re: EDF to bring 300MW of BESS online

#5

Post by nowty »

They make it hard to work out but its in MWp for 2 hours so its 313MWp and 626MWh capacity.

https://www.edf-re.uk/news-and-views/ed ... -projects/
18.7kW PV > 109MWh generated
Ripple 6.6kW Wind + 4.5kW PV > 26MWh generated
5 Other RE Coop's
105kWh EV storage
60kWh Home battery storage
40kWh Thermal storage
GSHP + A2A HP's
Rain water use > 510 m3
Lincs Robert
Posts: 214
Joined: Fri Mar 11, 2022 7:48 pm
Location: Lincolnshire

Re: EDF to bring 300MW of BESS online

#6

Post by Lincs Robert »

nowty wrote: Sat Aug 24, 2024 10:44 am They make it hard to work out but its in MWp for 2 hours so its 313MWp and 626MWh capacity.

https://www.edf-re.uk/news-and-views/ed ... -projects/