I don't read it as that. I read it as the page has updated on the 8th but the plants haven't since the 3rd- hence why you are seeing the discrepancy between the two sites and why generation is at 4.2 when it was at 4.8.Moxi wrote: ↑Wed Feb 08, 2023 10:30 am That just means those units havent changed their forecast but the sites updated for the 8th Feb now and Torness is still on the bars and heysham stage 2 still has a unit offload refuelling as per their stated 3rd Feb update thats extended for turbine vibration investigations and stage 1 has a reactor offline for refuelling due back on the 17th.
The main thing I was trying to note was Torness was back on load according to EDF but terravolt still shows one unit off.
Moxi
It states
Torness Last updated: 03 Feb 2023 14.38hrs 'Generation (MW) data as at: 03 Feb 2023 14.00hrs'