Big tunnel dig complete - seems to be making some progress

https://renews.biz/95006/sse-completes- ... as-tunnel/
Tesla Model 3 Performance
Oversees an 11kWp solar array at work
dan_b
Posts: 2404
Joined: Tue Jun 15, 2021 10:16 am
Location: SW London

Re: Coire Glas progress?

#12

Post by dan_b »

Video on progress at the new pumped hydro scheme now in development

Tesla Model 3 Performance
Oversees an 11kWp solar array at work
dan_b
Posts: 2404
Joined: Tue Jun 15, 2021 10:16 am
Location: SW London

Re: Coire Glas progress?

#13

Post by dan_b »

Interesting article about the exploratory "adit" tunnel dig and the conditions found underground.

https://www.newcivilengineer.com/in-dep ... 1-11-2024/
Tesla Model 3 Performance
Oversees an 11kWp solar array at work
AE-NMidlands
Posts: 2105
Joined: Wed Jun 02, 2021 6:10 pm

Re: Coire Glas progress?

#14

Post by AE-NMidlands »

interesting bit at the end:
According to the project team, 28% of the people that worked on this project phase are Scottish Highland residents.

The benefits to the local community and economy will be magnified if SSE Renewables decides to make the investment into the £1.5bn scheme, which will depend on the government’s delivery of the cap-and-floor mechanism. Through this mechanism, which was announced in October, investors will have guaranteed revenues above an agreed floor and will limit revenues to an agreed cap for the benefit of consumers.
2.0 kW/4.62 MWh pa in Ripples, 4.5 kWp W-facing pv, 9.5 kWh batt
30 solar thermal tubes, 2MWh pa in Stockport, plus Congleton and Kinlochbervie Hydros,
Most travel by bike, walking or bus/train. Veg, fruit - and Bees!
Post Reply