Gwynedd tidal project 'mothballed' due to bad grid connection

Water turbines and anything associated
Post Reply
AE-NMidlands
Posts: 1815
Joined: Wed Jun 02, 2021 6:10 pm

Gwynedd tidal project 'mothballed' due to bad grid connection

#1

Post by AE-NMidlands »

We don't get much news on hydro, and this is bad...
https://www.dailypost.co.uk/news/north- ... e-26192312
Gwynedd tidal project 'mothballed' due to bad grid connection
The Enlli project - between Ynys Enlli and Pen Pen Llŷn (Peninsula) - had secured £1.2m in Welsh Government funding
/
A spokesman said: “Due to a range of site-specific factors, including revenue support limitations and grid and cable routing constraints, the project will be mothballed from March 2023. This has been a difficult decision, but the issues identified mean it is not currently economically viable to develop a project there.

“If the grid on the Llyn is strengthened, the tidal project in Bardsey Sound would become viable and offer significant opportunities for local regeneration in the future.
2.0 kW/4.62 MWhr pa in Ripples, 4.5 kWp W-facing pv, 9.5 kWhr batt
30 solar thermal tubes, 2MWhr pa in Stockport, plus Congleton and Kinlochbervie Hydros,
Most travel by bike, walking or bus/train. Veg, fruit - and Bees!
Swwils
Posts: 530
Joined: Sat Feb 26, 2022 12:58 pm

Re: Gwynedd tidal project 'mothballed' due to bad grid connection

#2

Post by Swwils »

Ah yes those pesky site specific "revenue support limitations" LOL.
dan_b
Posts: 1860
Joined: Tue Jun 15, 2021 10:16 am
Location: SW London

Re: Gwynedd tidal project 'mothballed' due to bad grid connection

#3

Post by dan_b »

Urgh - access to the network with a sufficient power connection is always a problem. And an expensive one. What a shame/ridiculous lack of ambition.
Tesla Model 3 Performance
Oversees an 11kWp solar array at work
Post Reply