Moxi wrote: ↑Tue Jan 24, 2023 4:09 pm
I note that they speak of turbine erecting in August for the first units which is promising- I wonder if they commission them one by one or all together ?
Moxi
I imagine that would be dependant on the grid connection date.
For WT1 that was over 3 months after the turbine was built.
Reasons cited for the delay was Cable availability, Covid and Wayleave sign off.
Unfortunately it was the 3 most productive months of the year so getting WT2 online by Nov 23 is really important. On the other hand with the new 45% windfall tax, a few months delay may eliminate it in the first year, so maybe a small delay wont be a big deal.