Scottish onshore windfarm to be repowered

Wind turbines
smegal
Posts: 290
Joined: Fri Apr 08, 2022 7:51 pm

Re: Scottish onshore windfarm to be repowered

#21

Post by smegal »

nowty wrote: Tue Jul 18, 2023 7:19 pm
AE-NMidlands wrote: Tue Jul 18, 2023 6:27 pm I ws looking at the Ripple webbsite and found this (a bit late (Aug '22) but it seems relevant.) https://octopus.energy/blog/repowering- ... -turbines/ with
An illustration of an octopus extending a turbine blade... Preliminary sketch of the blade-lengthening process

Image
The process to build any new energy generator can be long and difficult. Everything from upgrading the local networks to getting planning permission can take ages. It typically takes seven years for a new turbine projects to get fully operational. Actual construction can be completed in a year: most of the time is taken up by lengthy planning and grid connection processes.

Tuning up our existing turbines can take far less time. We already have the most spot on data for wind speeds on site and local topography. Consultations with the local community are far quicker because they've already had a turbine in their neighbourhood – we're just adjusting what's already there. Because a lot of the most time-consuming work is already done, we can get more green electrons down the wires in months, not years.
It seems that raising the tower is an integral part of it, but no mention of re-equippingthe actual generator?
A
The way I read it (plus other info elsewhere) is it takes many years to get a new wind farm (seven years), but even though we have to go through the whole planning process again and re-build most things.

1) The local grid access point is there as it was before, so minimal grid work required.

2) The locals already have been used to the old windfarm so far less hostile to a new one so far easier to get the planning permission.

I believe these two aspects are the longest and hardest to get an otherwise greenfield wind farm operational from the drawing board.
One of the smaller (relatively speaking) wind turbine manufacturers was targeting repowering existing sites. In the example they gave, they targeted replacing a 275 kW turbine,l with their ~900 kW unit, and simply derating their turbine to 275 kW to keep the grid connection (and FiT) the same.
AE-NMidlands
Posts: 2063
Joined: Wed Jun 02, 2021 6:10 pm

Re: Scottish onshore windfarm to be repowered

#22

Post by AE-NMidlands »

I guess this is like having massively over-sized panels and ignoring the summer excess going unused so that you have enough further into the shoulder months, i.e being able to supply the permitted amount of electricity to the grid even as the wind drops away far below the point where the smaller turbine would have stalled.
Effectively multiplying the CF by 900 over 275?
2.0 kW/4.62 MWh pa in Ripples, 4.5 kWp W-facing pv, 9.5 kWh batt
30 solar thermal tubes, 2MWh pa in Stockport, plus Congleton and Kinlochbervie Hydros,
Most travel by bike, walking or bus/train. Veg, fruit - and Bees!
User avatar
Joeboy
Posts: 8154
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Scottish onshore windfarm to be repowered

#23

Post by Joeboy »

AE-NMidlands wrote: Wed Jul 19, 2023 10:12 am I guess this is like having massively over-sized panels and ignoring the summer excess going unused so that you have enough further into the shoulder months, i.e being able to supply the permitted amount of electricity to the grid even as the wind drops away far below the point where the smaller turbine would have stalled.
Effectively multiplying the CF by 900 over 275?
It would be good if the turbines could just output at their design capacity and the fit paid on 30% generation only with the remainder being bought on another contract. Its only paperwork... if the remainder of the site components can take the extra load.

It would be interesting to hear how it plays out?
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
AE-NMidlands
Posts: 2063
Joined: Wed Jun 02, 2021 6:10 pm

Re: Scottish onshore windfarm to be repowered

#24

Post by AE-NMidlands »

Joeboy wrote: Wed Jul 19, 2023 10:16 am
AE-NMidlands wrote: Wed Jul 19, 2023 10:12 am I guess this is like having massively over-sized panels and ignoring the summer excess going unused so that you have enough further into the shoulder months, i.e being able to supply the permitted amount of electricity to the grid even as the wind drops away far below the point where the smaller turbine would have stalled.
Effectively multiplying the CF by 900 over 275?
It would be good if the turbines could just output at their design capacity and the fit paid on 30% generation only with the remainder being bought on another contract. Its only paperwork... if the remainder of the site components can take the extra load.

It would be interesting to hear how it plays out?
I took it that "derating their turbine to 275 kW to keep the grid connection (and FiT) the same" was the crucial bit - avoiding the complications of any paperwork at all, let alone re-engineering!
2.0 kW/4.62 MWh pa in Ripples, 4.5 kWp W-facing pv, 9.5 kWh batt
30 solar thermal tubes, 2MWh pa in Stockport, plus Congleton and Kinlochbervie Hydros,
Most travel by bike, walking or bus/train. Veg, fruit - and Bees!
User avatar
Joeboy
Posts: 8154
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Scottish onshore windfarm to be repowered

#25

Post by Joeboy »

AE-NMidlands wrote: Wed Jul 19, 2023 10:20 am
Joeboy wrote: Wed Jul 19, 2023 10:16 am
AE-NMidlands wrote: Wed Jul 19, 2023 10:12 am I guess this is like having massively over-sized panels and ignoring the summer excess going unused so that you have enough further into the shoulder months, i.e being able to supply the permitted amount of electricity to the grid even as the wind drops away far below the point where the smaller turbine would have stalled.
Effectively multiplying the CF by 900 over 275?
It would be good if the turbines could just output at their design capacity and the fit paid on 30% generation only with the remainder being bought on another contract. Its only paperwork... if the remainder of the site components can take the extra load.

It would be interesting to hear how it plays out?
I took it that "derating their turbine to 275 kW to keep the grid connection (and FiT) the same" was the crucial bit - avoiding the complications of any paperwork at all, let alone re-engineering!
Fair enough. I just like to see stuff running flat out! :twisted:
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
Countrypaul
Posts: 573
Joined: Sun Jul 18, 2021 11:50 am

Re: Scottish onshore windfarm to be repowered

#26

Post by Countrypaul »

AE-NMidlands wrote: Wed Jul 19, 2023 10:12 am I guess this is like having massively over-sized panels and ignoring the summer excess going unused so that you have enough further into the shoulder months, i.e being able to supply the permitted amount of electricity to the grid even as the wind drops away far below the point where the smaller turbine would have stalled.
Effectively multiplying the CF by 900 over 275?
I suppose it depends on how they are derating the WT. If they are fitting smaller blades so that output peaks at 27kW, the results could be very different from furling the blades to limit peak outpu at 275kW,

If FITs are paid, would increasing the WT to 900 from 275 mean that only 275/900 worth of output is eligible for FITs similar to fitting more PV panels at home?
User avatar
nowty
Posts: 5833
Joined: Mon May 31, 2021 2:36 pm
Location: South Coast

Re: Scottish onshore windfarm to be repowered

#27

Post by nowty »

Countrypaul wrote: Wed Jul 19, 2023 10:44 am If FITs are paid, would increasing the WT to 900 from 275 mean that only 275/900 worth of output is eligible for FITs similar to fitting more PV panels at home?
Yes, I just checked the latest FIT guidance doc, the pro rata'ing of the FIT rate (on a extension) is not in the specific PV rules section. Therefore its common to all FIT generation technologies.
18.7kW PV > 109MWh generated
Ripple 6.6kW Wind + 4.5kW PV > 26MWh generated
5 Other RE Coop's
105kWh EV storage
60kWh Home battery storage
40kWh Thermal storage
GSHP + A2A HP's
Rain water use > 510 m3
smegal
Posts: 290
Joined: Fri Apr 08, 2022 7:51 pm

Re: Scottish onshore windfarm to be repowered

#28

Post by smegal »

Countrypaul wrote: Wed Jul 19, 2023 10:44 am
AE-NMidlands wrote: Wed Jul 19, 2023 10:12 am I guess this is like having massively over-sized panels and ignoring the summer excess going unused so that you have enough further into the shoulder months, i.e being able to supply the permitted amount of electricity to the grid even as the wind drops away far below the point where the smaller turbine would have stalled.
Effectively multiplying the CF by 900 over 275?
I suppose it depends on how they are derating the WT. If they are fitting smaller blades so that output peaks at 27kW, the results could be very different from furling the blades to limit peak outpu at 275kW,

If FITs are paid, would increasing the WT to 900 from 275 mean that only 275/900 worth of output is eligible for FITs similar to fitting more PV panels at home?
The derating of the turbine is on the electrical side. The mechanical bits such as the blades would be unaltered.
AE-NMidlands
Posts: 2063
Joined: Wed Jun 02, 2021 6:10 pm

Re: Scottish onshore windfarm to be repowered

#29

Post by AE-NMidlands »

smegal wrote: Wed Jul 19, 2023 11:05 am
Countrypaul wrote: Wed Jul 19, 2023 10:44 am
AE-NMidlands wrote: Wed Jul 19, 2023 10:12 am I guess this is like having massively over-sized panels and ignoring the summer excess going unused so that you have enough further into the shoulder months, i.e being able to supply the permitted amount of electricity to the grid even as the wind drops away far below the point where the smaller turbine would have stalled.
Effectively multiplying the CF by 900 over 275?
I suppose it depends on how they are derating the WT. If they are fitting smaller blades so that output peaks at 27kW, the results could be very different from furling the blades to limit peak outpu at 275kW,

If FITs are paid, would increasing the WT to 900 from 275 mean that only 275/900 worth of output is eligible for FITs similar to fitting more PV panels at home?
The derating of the [bigger] turbine is on the electrical side. The mechanical bits such as the blades would be unaltered...
... so that your bigger blades can continue delivering 275kW down to a much lower windspeed. As I said, isn't that like massively boosting the CF?
2.0 kW/4.62 MWh pa in Ripples, 4.5 kWp W-facing pv, 9.5 kWh batt
30 solar thermal tubes, 2MWh pa in Stockport, plus Congleton and Kinlochbervie Hydros,
Most travel by bike, walking or bus/train. Veg, fruit - and Bees!
smegal
Posts: 290
Joined: Fri Apr 08, 2022 7:51 pm

Re: Scottish onshore windfarm to be repowered

#30

Post by smegal »

AE-NMidlands wrote: Wed Jul 19, 2023 11:43 am
smegal wrote: Wed Jul 19, 2023 11:05 am
Countrypaul wrote: Wed Jul 19, 2023 10:44 am

I suppose it depends on how they are derating the WT. If they are fitting smaller blades so that output peaks at 27kW, the results could be very different from furling the blades to limit peak outpu at 275kW,

If FITs are paid, would increasing the WT to 900 from 275 mean that only 275/900 worth of output is eligible for FITs similar to fitting more PV panels at home?
The derating of the [bigger] turbine is on the electrical side. The mechanical bits such as the blades would be unaltered...
... so that your bigger blades can continue delivering 275kW down to a much lower windspeed. As I said, isn't that like massively boosting the CF?
Yes, significantly boosting the CF.

Max power would be at around 7 m/s instead of 15 m/s. Cut out wind speed would be unaltered.
Post Reply