Agile or Go?

Inskip75
Posts: 66
Joined: Thu Jun 10, 2021 6:42 am

Re: Agile or Go?

#11

Post by Inskip75 »

I've just swapped from Agile to Go - too few drops on Agile and with an EV and Autumn closing the cheap Go period better than the hope of a cheap period with Agile. Think the Go prices will be on the up soon.
5.6kW PV
0.8kW WT1 and 1.2kW WT2
9.6kWh batteries
3.5kW+2.5kW ASHP
Zappi
Seat Mii Electric
User avatar
nowty
Posts: 5792
Joined: Mon May 31, 2021 2:36 pm
Location: South Coast

Re: Agile or Go?

#12

Post by nowty »

Inskip75 wrote: Wed Jul 28, 2021 8:59 pm I've just swapped from Agile to Go - too few drops on Agile and with an EV and Autumn closing the cheap Go period better than the hope of a cheap period with Agile. Think the Go prices will be on the up soon.
Yes as you can see from Zarch's website, the last 7 days illustrate it too well. But also the fixed 24 month Octopus tariff which I could switch to, is now 19.75p per kWh, much higher than the peak rate period of Go, which makes no sense at all.

Image
18.7kW PV > 109MWh generated
Ripple 6.6kW Wind + 4.5kW PV > 26MWh generated
5 Other RE Coop's
105kWh EV storage
60kWh Home battery storage
40kWh Thermal storage
GSHP + A2A HP's
Rain water use > 510 m3
Inskip75
Posts: 66
Joined: Thu Jun 10, 2021 6:42 am

Re: Agile or Go?

#13

Post by Inskip75 »

nowty wrote: Wed Jul 28, 2021 9:36 pm
Inskip75 wrote: Wed Jul 28, 2021 8:59 pm I've just swapped from Agile to Go - too few drops on Agile and with an EV and Autumn closing the cheap Go period better than the hope of a cheap period with Agile. Think the Go prices will be on the up soon.
Yes as you can see from Zarch's website, the last 7 days illustrate it too well. But also the fixed 24 month Octopus tariff which I could switch to, is now 19.75p per kWh, much higher than the peak rate period of Go, which makes no sense at all.

Image
Yes - I've been checking the graphs and Octopus app and the prices of Agile were just going up and up.......
5.6kW PV
0.8kW WT1 and 1.2kW WT2
9.6kWh batteries
3.5kW+2.5kW ASHP
Zappi
Seat Mii Electric
User avatar
Stinsy
Posts: 2850
Joined: Wed Jun 02, 2021 1:09 pm

Re: Agile or Go?

#14

Post by Stinsy »

nowty wrote: Wed Jul 28, 2021 9:36 pm
Inskip75 wrote: Wed Jul 28, 2021 8:59 pm I've just swapped from Agile to Go - too few drops on Agile and with an EV and Autumn closing the cheap Go period better than the hope of a cheap period with Agile. Think the Go prices will be on the up soon.
Yes as you can see from Zarch's website, the last 7 days illustrate it too well. But also the fixed 24 month Octopus tariff which I could switch to, is now 19.75p per kWh, much higher than the peak rate period of Go, which makes no sense at all.

Image
Don’t forget there are different standing charges on these tariffs.
12x 340W JA Solar panels (4.08kWp)
3x 380W JA Solar panels (1.14kWp)
5x 2.4kWh Pylontech batteries (12kWh)
LuxPower inverter/charger

(Artist formally known as ******, well it should be obvious enough to those for whom such things are important.)
marshman
Posts: 614
Joined: Thu Jun 17, 2021 7:58 pm

Re: Agile or Go?

#15

Post by marshman »

__
Last edited by marshman on Sun Jun 11, 2023 9:59 pm, edited 1 time in total.
Zarch
Posts: 10
Joined: Tue Jul 27, 2021 7:47 pm

Re: Agile or Go?

#16

Post by Zarch »

Stinsy wrote: Thu Jul 29, 2021 7:35 am
Don’t forget there are different standing charges on these tariffs.
4p per day difference

Agile 21p
Go 25p
5.1 of panels on 3.68 Solaredge inverter
12kWh Lux AC and Pylontech battery combo
Zappi Charger for our 50 kWh Peugeot e208
Creator of energy-stats.uk and @energystatsuk Twitter account
User avatar
nowty
Posts: 5792
Joined: Mon May 31, 2021 2:36 pm
Location: South Coast

Re: Agile or Go?

#17

Post by nowty »

Zarch wrote: Thu Jul 29, 2021 10:01 am
Stinsy wrote: Thu Jul 29, 2021 7:35 am
Don’t forget there are different standing charges on these tariffs.
4p per day difference

Agile 21p
Go 25p
Thats hardly much difference and even my fathers 24 month fixed deal with Octopus is 24.38p standing charge and 18.1p / kWh.

I.e. almost the same standing charge as Go and the price per kWh is more than the peak price on Go so even without any time shifting he would save money. I am just waiting for Octopus to be able to read his Smets 1 meter before swapping him over to it.
18.7kW PV > 109MWh generated
Ripple 6.6kW Wind + 4.5kW PV > 26MWh generated
5 Other RE Coop's
105kWh EV storage
60kWh Home battery storage
40kWh Thermal storage
GSHP + A2A HP's
Rain water use > 510 m3
User avatar
nowty
Posts: 5792
Joined: Mon May 31, 2021 2:36 pm
Location: South Coast

Re: Agile or Go?

#18

Post by nowty »

And the current unplanned outage of 3 of Heysham's nuclear reactors aren't helping.

https://www.edfenergy.com/energy/power- ... y-statuses


Never seen Nuclear so low at 3.31GW.

https://www.gridwatch.templar.co.uk/
18.7kW PV > 109MWh generated
Ripple 6.6kW Wind + 4.5kW PV > 26MWh generated
5 Other RE Coop's
105kWh EV storage
60kWh Home battery storage
40kWh Thermal storage
GSHP + A2A HP's
Rain water use > 510 m3
User avatar
Joeboy
Posts: 8096
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Agile or Go?

#19

Post by Joeboy »

Joeboy wrote: Wed Jul 28, 2021 2:08 pm While speaking to the guy at Octopus it turns out that after the faulty comms module was changed out and all communications on this change being logged that Octopus were trying to communicate with the old comms module. They are now commissioning the new comms module from their end and hope this will solve the problem, fingers crossed.... :roll:
Had word back from Joe at Octopus and the new comms unit is now hooked into their system, all going well we'll be back up and running datawise by early next week. The essential lesson for me has been direct contact with Octopus by phone trumps mucho e mails.
Last edited by Joeboy on Fri Jul 30, 2021 8:30 pm, edited 2 times in total.
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
Stinsy
Posts: 2850
Joined: Wed Jun 02, 2021 1:09 pm

Re: Agile or Go?

#20

Post by Stinsy »

Joeboy wrote: Fri Jul 30, 2021 7:30 pm
Joeboy wrote: Wed Jul 28, 2021 2:08 pm While speaking to the guy at Octopus it turns out that after the faulty comms module was changed out and all communications on this change being logged that Octopus were trying to communicate with the old comms module. They are now commissioning the new comms module from their end and hope this will solve the problem, fingers crossed.... :roll:
Had word back from Joe at Octopus and the new comms unit is now hooked into their system, all going well we'll be back up and running datawise by early next week. The lessential for me has been direct contact with Octopus by phone trumps mucho e mails.
+1 for Octopus phone support being good and their email support being rubbish.
12x 340W JA Solar panels (4.08kWp)
3x 380W JA Solar panels (1.14kWp)
5x 2.4kWh Pylontech batteries (12kWh)
LuxPower inverter/charger

(Artist formally known as ******, well it should be obvious enough to those for whom such things are important.)