Second system extension extension.

User avatar
Joeboy
Posts: 8102
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Second system extension extension.

#251

Post by Joeboy »

Fintray wrote: Thu Jul 07, 2022 7:06 pm
Joeboy wrote: Thu Jul 07, 2022 6:00 pm We have no fear of the grid or grey skies! :ugeek:
Try saying that when the dreich days of winter group together for days on end... :D
I shall! Sunny side up type. BTW, its month at a time. :D
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
Fintray
Posts: 1558
Joined: Mon May 31, 2021 6:37 pm
Location: Aberdeenshire

Re: Second system extension extension.

#252

Post by Fintray »

Joeboy wrote: Thu Jul 07, 2022 7:17 pm
Fintray wrote: Thu Jul 07, 2022 7:06 pm
Joeboy wrote: Thu Jul 07, 2022 6:00 pm We have no fear of the grid or grey skies! :ugeek:
Try saying that when the dreich days of winter group together for days on end... :D
I shall! Sunny side up type. BTW, its month at a time. :D
I was trying to be optimistic!
3.87kWp PV
10.24kWp PV SolarEdge system
Tesla Powerwall 2
100 x 47mm Navitron tubes (still being installed!) Now likely to be removed for more PV.
MK2 PV router DHW diverter
Morso 5kW WBS
Vaillant AroTherm 10kW ASHP
Nissan Leaf
User avatar
Joeboy
Posts: 8102
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Second system extension extension.

#253

Post by Joeboy »

Fintray wrote: Thu Jul 07, 2022 7:20 pm
Joeboy wrote: Thu Jul 07, 2022 7:17 pm
Fintray wrote: Thu Jul 07, 2022 7:06 pm

Try saying that when the dreich days of winter group together for days on end... :D
I shall! Sunny side up type. BTW, its month at a time. :D
I was trying to be optimistic!
Side gate will be open, just come through the back.
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
Joeboy
Posts: 8102
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Second system extension extension.

#254

Post by Joeboy »

Went for it this afternoon and the 3 panels are in and working.

Overcast here

Solaredge 16 panel array is putting out 800W
Victron 15 panel array is putting out 700W



Image

Image

Away to tidy up, knackered but very 😊.

Found one melted MC4 connector today, will change out tomorrow. :|

Turns out an old tit like me CAN get 400W panels on shoulder, up a ladder then up a bungalow roof. Getting too old for this... :twisted:

Looking forward to seeing it all cranking away tomorrow in the clear spells, more EV power and it was great to see that fabled 1.5kW be the figure when I switched it back on. As I said before, you can do a lot with small amounts of power generated over long periods. While up there it turns out that there is a possible space for three more panels but in all honesty I don't think i need them...
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
nowty
Posts: 5793
Joined: Mon May 31, 2021 2:36 pm
Location: South Coast

Re: Second system extension extension.

#255

Post by nowty »

I had you down on the secret list for 7000kWh for annual PV generation, what do you reckon now, 8000kWh ? ;)
18.7kW PV > 109MWh generated
Ripple 6.6kW Wind + 4.5kW PV > 26MWh generated
5 Other RE Coop's
105kWh EV storage
60kWh Home battery storage
40kWh Thermal storage
GSHP + A2A HP's
Rain water use > 510 m3
User avatar
Joeboy
Posts: 8102
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Second system extension extension.

#256

Post by Joeboy »

nowty wrote: Fri Jul 08, 2022 5:27 pm I had you down on the secret list for 7000kWh for annual PV generation, what do you reckon now, 8000kWh ? ;)
I have no idea! 7,500kWh, the split orientation and shading kills it for BIG figures. Great though, there is 1.6kW coming in the now. :lol:
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
Fintray
Posts: 1558
Joined: Mon May 31, 2021 6:37 pm
Location: Aberdeenshire

Re: Second system extension extension.

#257

Post by Fintray »

Joeboy wrote: Fri Jul 08, 2022 5:06 pm Went for it this afternoon and the 3 panels are in and working.

Turns out an old tit like me CAN get 400W panels on shoulder, up a ladder then up a bungalow roof. Getting too old for this... :twisted:
Kin'ell no messing about with you Joe, you could have had them up and running hours ago if I hadn't come round for a tour.
Your only too old if you fall off! :shock:
3.87kWp PV
10.24kWp PV SolarEdge system
Tesla Powerwall 2
100 x 47mm Navitron tubes (still being installed!) Now likely to be removed for more PV.
MK2 PV router DHW diverter
Morso 5kW WBS
Vaillant AroTherm 10kW ASHP
Nissan Leaf
User avatar
Joeboy
Posts: 8102
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Second system extension extension.

#258

Post by Joeboy »

Fintray wrote: Fri Jul 08, 2022 5:44 pm
Joeboy wrote: Fri Jul 08, 2022 5:06 pm Went for it this afternoon and the 3 panels are in and working.

Turns out an old tit like me CAN get 400W panels on shoulder, up a ladder then up a bungalow roof. Getting too old for this... :twisted:
Kin'ell no messing about with you Joe, you could have had them up and running hours ago if I hadn't come round for a tour.
Your only too old if you fall off! :shock:
It was ALL time well spent. Excellent to see ye.
Those panels get damn heavy near the top of the incline, then a wee breeze springs up and it's sail city, brown trousers.
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
Joeboy
Posts: 8102
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Second system extension extension.

#259

Post by Joeboy »

Just sitting back watching it happen.

Image
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
nowty
Posts: 5793
Joined: Mon May 31, 2021 2:36 pm
Location: South Coast

Re: Second system extension extension.

#260

Post by nowty »

Joeboy wrote: Fri Jul 08, 2022 5:35 pm
nowty wrote: Fri Jul 08, 2022 5:27 pm I had you down on the secret list for 7000kWh for annual PV generation, what do you reckon now, 8000kWh ? ;)
I have no idea! 7,500kWh, the split orientation and shading kills it for BIG figures. Great though, there is 1.6kW coming in the now. :lol:
I'll update you for 7,500 kWh then, as your going to end up like me in curtailment land. :evil:

But when its curtailed you don't need it. :twisted:
18.7kW PV > 109MWh generated
Ripple 6.6kW Wind + 4.5kW PV > 26MWh generated
5 Other RE Coop's
105kWh EV storage
60kWh Home battery storage
40kWh Thermal storage
GSHP + A2A HP's
Rain water use > 510 m3
Post Reply