High altitude hydro

Water turbines and anything associated
dan_b
Posts: 2329
Joined: Tue Jun 15, 2021 10:16 am
Location: SW London

High altitude hydro

#1

Post by dan_b »

A hydro plant at 5000m? That's a long way up!

https://electrek.co/2023/03/16/this-hyd ... sea-level/
Tesla Model 3 Performance
Oversees an 11kWp solar array at work
User avatar
nowty
Posts: 5886
Joined: Mon May 31, 2021 2:36 pm
Location: South Coast

Re: High altitude hydro

#2

Post by nowty »

2.2 GW. :twisted:

EDIT - Also a capacity factor of 37.8 %.
Last edited by nowty on Sat Mar 18, 2023 5:10 pm, edited 1 time in total.
18.7kW PV > 109MWh generated
Ripple 6.6kW Wind + 4.5kW PV > 27MWh generated
6 Other RE Coop's
105kWh EV storage
60kWh Home battery storage
40kWh Thermal storage
GSHP + A2A HP's
Rain water use > 510 m3
dan_b
Posts: 2329
Joined: Tue Jun 15, 2021 10:16 am
Location: SW London

Re: High altitude hydro

#3

Post by dan_b »

Also it says it integrates solar and storage at the same site, which is interesting.
You'd think with such a high elevation they could make it into a really mahoosive pumped hydro scheme with a lower lake much lower down?
Tesla Model 3 Performance
Oversees an 11kWp solar array at work
User avatar
Paul_F
Posts: 210
Joined: Tue Jun 01, 2021 6:31 pm

Re: High altitude hydro

#4

Post by Paul_F »

dan_b wrote: Sat Mar 18, 2023 11:57 amAlso it says it integrates solar and storage at the same site, which is interesting.
You'd think with such a high elevation they could make it into a really mahoosive pumped hydro scheme with a lower lake much lower down?
It's in the Tibetan plateau, so the available drop might be quite limited. It's also a very long way from anywhere with a high capacity factor, both making pumped storage harder. Probably not worth the aggrevation.
CrofterMannie
Posts: 101
Joined: Sun Jun 13, 2021 5:29 pm

Re: High altitude hydro

#5

Post by CrofterMannie »

Altitude is fairly meaningless without knowing the head.

I visited the Grande Dixance dam a number of years ago which has a head of over 1800m. Is that still the highest in the world?

There must be some kind of practical limit to the pressure that can be managed on these projects. 1800m gives about 180 bar pressure or 540 tons per square meter. A bit of blue pipe won't cut it with these pressures!
8kw solar
ETA log boiler
5ha woodland
MG5EV
John_S
Posts: 377
Joined: Wed Jun 02, 2021 10:03 am
Location: West London

Re: High altitude hydro

#6

Post by John_S »

From Wikipedia

The water travels down a long penstock from the Grande Dixence Dam before reaching the Bieudron Power Station 1,883 m down. The water spins three pelton turbines, generating a combined capacity of 1,269 MW.The power station was built between 1993 and 1998 at a cost of US$1.2 billion.

The Bieudron Power Station alone holds three world records, for the height of its head (1,883 m), the output of each Pelton turbine (3 × 423 MW) and the output per pole of the generators (35.7 MVA). It was taken out of service in December 2000 after the rupture of a penstock. The power station became partially operational in December 2009 and fully operational in 2010.


So two years after it was built, it was taken out of service for 9 years. Obviously a 1,883m head presents engineering challenges

There are two other power stations supplied from Grand Dixence. An old small one with a head of 1,745m and an intermediate sized pair which first goes to power station half way down and then to a second one at the bottom.

I visited the dam in 2015.
Moxi
Posts: 2327
Joined: Sun Oct 31, 2021 3:46 pm

Re: High altitude hydro

#7

Post by Moxi »

I'm surprised they state a penstock for holding back the static head ? I would expect that to be the realms of a specialist control valve like the larner johnson.

Moxi
smegal
Posts: 295
Joined: Fri Apr 08, 2022 7:51 pm

Re: High altitude hydro

#8

Post by smegal »

Moxi wrote: Tue Mar 21, 2023 2:10 pm I'm surprised they state a penstock for holding back the static head ? I would expect that to be the realms of a specialist control valve like the larner johnson.

Moxi
The pressure pipe on a hydro scheme is called the penstock, as opposed to penstock valves.

One of the more interesting hydro valve arrangements is at Dinorwig with the rapid closing valves and surge shaft.
openspaceman
Posts: 662
Joined: Mon Mar 21, 2022 7:37 pm

Re: High altitude hydro

#9

Post by openspaceman »

smegal wrote: Tue Mar 21, 2023 5:03 pm

One of the more interesting hydro valve arrangements is at Dinorwig with the rapid closing valves and surge shaft.
So that is what the smaller pond is half way down and south of Elidir Fach, to reduce the hammering effect when the valves close?
Morso S11
FIT
16 Sharp PV panels facing WSW 4kW
Solarmax 4200S inverter
Non FIT
3 Canadian solar DC coupled 1.75kW facing SSE
Storage
Growatt SPA3000TL BL inverter ac coupled
Growatt GBLI6532 6.5kWh lithium phosphate battery
smegal
Posts: 295
Joined: Fri Apr 08, 2022 7:51 pm

Re: High altitude hydro

#10

Post by smegal »

openspaceman wrote: Tue Mar 21, 2023 6:07 pm
smegal wrote: Tue Mar 21, 2023 5:03 pm

One of the more interesting hydro valve arrangements is at Dinorwig with the rapid closing valves and surge shaft.
So that is what the smaller pond is half way down and south of Elidir Fach, to reduce the hammering effect when the valves close?
I don't know the pond itself, but I'd assume so. I just searched YouTube and saw a video where the valves closed super fast.
Post Reply