Being a microgeneration site for the grid

Post Reply
User avatar
Joeboy
Posts: 8096
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Being a microgeneration site for the grid

#1

Post by Joeboy »

I didn't want to hijack Snuggy's panel install thread so i'll continue here.

I'm testing the Goodwe Hybrid discharge side today. I'm impressed they way it throttles the battery rate to match the shortfall to the Solaredge generation to keep as close to the 3.6kW limit as possible. The SOC discharge rate setting seems to work as well so i won't flatten the battery. :fight:

I've had a look at pricing and if i'm right I just loes the export side of the FIT? Had a quick look at figures and If i keep the generation side of the FIT on a conservative view even just May to Sept this is a no brainer.

Off to apply! :)

Anyone been ballsy enough to go for Export Agile?
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
Joeboy
Posts: 8096
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Being a microgeneration site for the grid

#2

Post by Joeboy »

Well that was simple enough. Although i don't have a inform DNO letter from installer and they went tits up years ago. We'll see how much of a problem that becomes. :facepalm:

Can't see it being a hassle as its a 3.6kW limited export and thats on the MCS? Its funny, even just messing about this morning with the discharge side it all clicked into place regarding the potential I have here (April to Sept).

They're saying 6 weeks but that I assume is a generic timeframe, who beat the 6 week window? Hopefully it will go faster (get it GO faster, ah i'm wasted here)! :)
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
nowty
Posts: 5791
Joined: Mon May 31, 2021 2:36 pm
Location: South Coast

Re: Being a microgeneration site for the grid

#3

Post by nowty »

I did not have one either, I emailed my DNO and they emailed me back within a couple of days confirming they know about my system. A screenshot of the email was enough for Octopus.

If your DNO is Scottish and Southern the email is, connections@ssen.co.uk
18.7kW PV > 109MWh generated
Ripple 6.6kW Wind + 4.5kW PV > 26MWh generated
5 Other RE Coop's
105kWh EV storage
60kWh Home battery storage
40kWh Thermal storage
GSHP + A2A HP's
Rain water use > 510 m3
NoraBatty
Posts: 134
Joined: Sat Mar 23, 2024 10:40 am

Re: Being a microgeneration site for the grid

#4

Post by NoraBatty »

I plan on looking again at agile export once the system is up and running. Currently i am on their fixed 15p rate, and although not been paying too much attention to outgoing rate fluctuations, fixed seems to be the better option, and the opposite, agile better for incoming.
2.7kw Canadian solar. roof. 3kw solis G98 mcs
12kw midea ASHP
200l hot water
3152W RE, Whitelaw Brae
Octopus agile/outgoing fixed 15p

Planned;
Hybrid system
43kwh eve batteries, 3x16 280A
6-8+kw solar, DC connected.
NoraBatty
Posts: 134
Joined: Sat Mar 23, 2024 10:40 am

Re: Being a microgeneration site for the grid

#5

Post by NoraBatty »

Will add, my latest dealings with ssen were :head-bang:
Refused to talk to me unless i was a qualified electrician and mcs installer.
I understand the need to make sure idiots arent jerry rigging their electicity, but they wouldnt even discuss my existing g98.

Fingers crossed you have better luck, or a different person on the end of the phone.
2.7kw Canadian solar. roof. 3kw solis G98 mcs
12kw midea ASHP
200l hot water
3152W RE, Whitelaw Brae
Octopus agile/outgoing fixed 15p

Planned;
Hybrid system
43kwh eve batteries, 3x16 280A
6-8+kw solar, DC connected.
User avatar
Fintray
Posts: 1558
Joined: Mon May 31, 2021 6:37 pm
Location: Aberdeenshire

Re: Being a microgeneration site for the grid

#6

Post by Fintray »

Joeboy wrote: Mon Jun 24, 2024 9:26 am Anyone been ballsy enough to go for Export Agile?
Looking back over the Agile export doesn't show many times above 15p/kWh so doubt it would be worth the effort.
3.87kWp PV
10.24kWp PV SolarEdge system
Tesla Powerwall 2
100 x 47mm Navitron tubes (still being installed!) Now likely to be removed for more PV.
MK2 PV router DHW diverter
Morso 5kW WBS
Vaillant AroTherm 10kW ASHP
Nissan Leaf
User avatar
Joeboy
Posts: 8096
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Being a microgeneration site for the grid

#7

Post by Joeboy »

Thank you all,
Mail away to SSEN, it does say on the MCS cert which i attached to SSEN that the DNO would be informed post install and commissioning. Hopefully it will a confirming letter return from them and onwards to Octopus with that. I went for fixed 15p. That's a decent hike up for my late through the door (last 6 months of the scheme running) FIT rate!
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
Joeboy
Posts: 8096
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Being a microgeneration site for the grid

#8

Post by Joeboy »

nowty wrote: Mon Jun 24, 2024 10:28 am I did not have one either, I emailed my DNO and they emailed me back within a couple of days confirming they know about my system. A screenshot of the email was enough for Octopus.

If your DNO is Scottish and Southern the email is, connections@ssen.co.uk
Thanks pal, much appreciated!
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
User avatar
Joeboy
Posts: 8096
Joined: Mon May 31, 2021 4:22 pm
Location: Inverurie

Re: Being a microgeneration site for the grid

#9

Post by Joeboy »

Hilarious,

My MCS cert has name, address, area etc, post code and then as a bottom line.... ENGLAND. :lol:

They must have confused Shires, absolute nuggets. :roll:
19.7kW PV SE, VI, HM, EN & DW
Ripple 7kW WT & Gen to date 19MWh
42kWh LFPO4 storage
95kWh Heater storage
12kWh 210ltr HWT.
73kWh HI5
Deep insulation, air leak ct'd home
Zoned GCH & Hive 2
WBSx2
Low energy bulbs
Veg patches & fruit trees
Adokforme
Posts: 621
Joined: Sun Sep 19, 2021 10:09 pm

Re: Being a microgeneration site for the grid

#10

Post by Adokforme »

Good luck with it all Joe, I've stuck with Go and the fixed 15p as not very good at keeping abreast of likely rate changes.
It did take a while to get onboard with Outgoing but we're there now and subsequently discovered we are limited to 12kW's export rate. So, you never know, but you may get a healthy uplift on your rate also. :xx:
Post Reply